Civil works - proposed concrete batching plant Neilsen's Holdings - Windsor
Image
Works included the construction of the following: Earthworks and embankment, Retaining Walls, Concrete Pavements, Stormwater Drainage, First Flush Tank, Recycle Pit, Washout Bays, Drive-over Bins including sheet piling and access shaft, Overhead Bins and Conveyor Pit including piled footings, pile-caps and columns, Piled footings and pile-caps for silos, Batch Control Room and Office including external walkways, stairs, doors, windows, air conditioning systems and mezzanine floors, Loading Shed including piled foundations, tilt up panels, structural steel, web grating, roller doors, Drivers Room, Bunded admixture including tanking, Fencing including perimeter chain wire, acoustic and timber, Services including power supply, yard security lighting, water supply, sewer, phone and intercoms, External Works including sewer, water, electricity, driveway extensions and street lighting
Client: Neilsen's Holdings
Approx. Value: $2.6m
 
University Of Queensland, Gatton Campus Sewage Treatment Plant - construction of new Chlorination Detention Basin
 
Construction of a new chlorination detention basin at the sewage treatment plant at the Gatton Campus for the University of Queensland.  Works include the following: Excavation, supplying, laying, jointing and backfilling of pipes forming part of the detention basin including connection to existing.  Construction of new internal wall within the existing detention chamber.  Construction of access chamber, temporary works and relocation of existing underground services.
Client: University of QLD (gatton Campus)
Approx. Value: $100k
 
Century Yuasa Batteries,
New Strip Mill Building Foundation Slab
 
Construction of the new concrete foundations and slab for the new strip mill building at the Carole Park factory.
Client: MPA Consulting Engineers
Approx. Value: $170k
 
Wuraga Road Subdivision, Bahrs Scrub
 
10 Lot Park Residential Subdivision self developed.  Works include project management, design management, approvals, earthworks, roadworks, drainage, electrical and water reticulation.
Client: Davbridge Constructions Pty Ltd
Approx. Value: $1.2m
 
Kremzow Road, Brendale
 
Construction of sewerage reticulation, water reticulation and associated works for warehouse development at Kremzow Road.
Client: Saunders & Partners
Approx. Value: $100k
 
Launder Wall Rectification, Clarifier No. 1, Cleveland Bay Sewerage Treatment Plant
 
This contract involves the demolition of the top 800mm of the existing 200mm thick singly reinforced launder drain wall and reconstruction as a 250mm thick wall with Class 40 concrete and two layers of steel reinforcement.  It also included the replacement of the clarifier bridge polyurethane drive wheels.
Client: Townsville City Council - Citiwater
Approx. Value: $100k
 

Coombabah WWPT Lagoons

 
The project involved works at Coombabah WWTP.  This work comprised of piling and concrete works for extension of existing inlet channels and reformation of existing earthen embankments to lagoons 3 and 4, supply and installation of flow diversion baffles, desluding of existing lagoons, and associated works. 
Client: Gold Coast City Council (Water)
Approx. Value: $1.9m
 

Reclamation Pit, Ipswich Foundry

 
Excavation, forming and construction of a reclamation pit (approx 10m long x 5m wide x 5m deep), including sheetpiling and supply of all materials.
Client: Bradken Industrial
Approx. Value: $95k
 
Woodridge Railway Station Intermodal Facility
 
The construction of a new Intermodal Transport Facility and associated Plaza Areas at Woodridge Railway Station, 26.50km Beenleigh Line.  This project involved flattening the subway pedestrian ramp for the disabled, bus and taxi awnings, landscaping and concrete paving to the Plaza area, a bus aisle and taxi rank and associated services works.
Client: Queensland Rail
Approx. Value: $690k